How to Lead a Pull Plan Session

Around 15% of builders are using Pull Planning (although only 9% are using the full Last Planner® System) on at least some of their projects, according to the AGC and McGraw Hill [1] . The challenge is how to get the most value in the shortest time during a pull planning session.

The authors of this blog have led and coached over 200 pull planning sessions in the last few years, co-authored a book on the subject, and led dozens of training sessions and webinars. We’ve seen it done right, done wrong, and learned from our mistakes and those of others. We’ve refined the leadership needs for pull planning and can say with confidence that leading a pull planning session takes “PEN”:

  • Preparation
  • Enthusiasm
  • Neutrality

Of course, you need to know construction, the concept of pull, the sequence of the backward pass and forward pass, how to jumpstart a team of trade foremen to “get them to the wall” and how to pull in the General Contractor/Design Builder’s (“GC/DB”) leadership, resources, and commitment. But for now, let’s focus on the “magic” of getting a group of 10-20 trade foremen – each with his/her own personality, experience, attitudes and needs – actively to collaborate in the pull planning session.

Preparation

It starts with preparation – yours and theirs. Everyone involved needs that “aha” moment when they realize that organized collaborative pull planning kicks butt compared to the “lone genius” most projects using P6 have. They’ve probably heard the statistics: 4-20 weeks saved on the schedule, doing 5 months worth of work in 3 months, doubling production in 6 weeks from $1.5 Million/Day to $3.0 Million/Day, and so on. However, it’s not real until you feel it.

We recommend the team spend 3-4 hours doing the Villego™ simulation. Until you’ve experienced it yourself, you simply don’t understand the brilliance of “pull”. For the session leader, it means preparing the materials to be used – post- its, Sharpies, plotter paper, flip chart, painters tape, laminated site plans or floor plans (elevations for skin), RFI logs, submittal logs, having the BIM model running, etc. It also means pulling the leadership team together and selecting in advance key milestones to be pulled with their target dates.



2. Enthusiasm

Once the session begins you must keep a steady and somewhat quickened/urgent pace to keep everyone’s attention and focus. The leader needs to be enthusiastic, both about the process and about the ability of each individual to contribute his/her unique skill, experience and knowledge to the team planning.

Set time expectations: “Ok, let’s get our tags up in 30 minutes, if you need help I’ve got 2 hands.” Cheerlead: “Great job, Frank! Come on, Greg, get those 3 tags up there before you write any more, the team needs your input on the wall.” Broker conversations. Listen for what we call “the hum” that occurs as the session hits its stride: the sound of multiple conversations about specific project elements or approaches. It’s not too loud, not too soft, and sounds like a wavy hum. Move around the room helping, encouraging, asking things like, “What else has to be in place to release this work?” and then make sure tags keep moving to the wall. Keep time, nudge, urge, “Ok we need to get to the next step, you’ve got 5 more minutes. You can do it!” Look, not everyone is that enthusiastic in real life. We know that. But a pull plan session is a “stage” and the leader has to play the part, so if you’re typically more reserved, think of it as an acting assignment. Play the role. Step it up. Use your voice, your body, and your movements to keep the planning focused and moving rapidly.





3. Neutrality

Why does the leader need to be neutral? Because the old paradigm of construction (which is 85% of the projects the trades are on) is top down command and control. There is no voice for “subs” and they aren’t allowed to say “no”. They may be expecting to get steamrolled by the GC/DBer. The trades are thinking: “Sure you want my input now, but in the end you’re going to tell us what to do, and we had better do it.” However, to work effectively pull planning needs a true collaborative team that trusts each other to tell it straight, give real durations (no hidden float), and make reliable promises and keep them. To get that kind of team spirit and collaboration, the leader must be neutral. It’s easy for us coaches to be neutral. We work for what is best for the project, aka “Project First”.

The leader needs to explain at the beginning of the session, “We want your honest input today. Sure we’ve thought through this and have a plan for how it could go, we wouldn’t have gotten this project without it. But that plan can always be improved with your experience and your input. So we’re going to figure this out together. And I’m going to stay neutral on what the better way to build this is until we’ve talked through the options, gamed them with our tags, and decided as a group what way will work to everyone’s advantage.” And as leader, if you can’t resist and you need to step out of your neutral role and advocate for one position, then hand the PEN to someone else to serve as the neutral leader for a few minutes. When you’ve advocated for your position, announce you’re taking the PEN back and now will be neutral again. If you do this, you will enhance your leadership authority and build more trust from the team.



These are just a few of the insights we’ve learned from lots of experience with pull planning. If you want more watch our recorded webinar, “How to Lead a Pull Plan Session” complete with photos, examples and plenty of tips.


Additional Resources:

1. How Lean Practices Represent the Future
2. Fauchier, Dan and Thais Alves, Last Planner is the Gateway to Lean Behaviors (IGLC 2013, Fortaleza Brazil), http://iglc.net/Papers/Details/898
3. Umstot, David and Dan Fauchier, Lean Project Delivery: Building Championship Project Teams, (2017, Amazon)


Featured Post

 

Lean Tools During Design & Preconstruction – IPD or Not

I wanted to start this blog post with the most important message I have for all those who read this – you don’t need to have an IPD project in order to successfully use lean tools during design and preconstruction! As you will see from the real life examples described later, in order to do so, all that’s needed is the right integrated environment.

Lean Transformation  Lean Design Read more

 

 

What is Integrated Project Delivery Part 2: Lean Operating System

This post is the 2nd of a 3 part series looking at Integrated Project Delivery. The first post focuses on IPD agreements (contracts), this post focuses on IPD as a Lean Operating System, and the final post focuses on culture.

To maximize the value of the contract structure, teams require a new work philosophy focused on efficiency and reliability. A Lean Operating System delivers customer value, through streamlined processes practicing continuous improvement.

Integrated Project Delivery Read more

 

 

Pull Planning in Design - Best Practices and Common Pitfalls

At the heart of most lean processes is the drive to reduce waste and increase reliability. The Last Planner System is no different. Over the last few years, construction teams have been able to utilize the The Last Planner System to reduce waste in terms of scheduling, production, and quality control, with a relatively high level of success.

Last Planner Read more

 

 

Zero Sum to Win-Win: An Australian Perspective on Integrated Project Delivery

In many parts of the World, contracting can seem like the modern-day equivalent of a Roman gladiatorial battle, where a single project cost blow-out can end a promising political career or bankrupt a once profitable company.

The rules of the contest are set out in the construction contract and rival teams of lawyers seek to negotiate their side an early advantage in the battle to come through the introduction of carefully crafted indemnities, notification regimes, liability caps and risk transfer, with little or no consideration as to whether the party that ends up liable for a risk is best able to manage it.

Integrated Project Delivery Read more

Copyright © 2015- Lean Construction Blog