Takt time planning - When the train falls off the tracks

Takt time planning is a great tool for aligning crews and creating flow on site. However, it’s still just a plan and it will inevitably fail at some point. One of the reasons for using takt time is not only to create flow, but also help pinpoint where the bottleneck is on site. In the long run that’s a good thing; don’t ignore your problems, they’ll just grow.

Aside from adding more crews, here are a few countermeasures to consider when executing a Takt time plan that’s gone off-beat.

Change the sequence

When the work starts, your assumptions may be proven wrong. If it’s going to be a universal issue through all the zones, it makes sense to change the sequence. Here are a few changes to consider:

1. Adjust the trade sequence but keep the same number of activities (e.g., maybe plumbing needs to go before electrical in-wall in all zones)
2. Change the sequence by adding activities to the sequence (e.g., framing with inspections may take longer, so split out inspections and make framing and inspections two separate activities)
3. Move the tasks within the activities themselves that make up the sequence. Typically, activities (e.g., electrical inwall, priority wall framing, etc.) contain several tasks within the activity. It may make sense to move work inside the activity to another part of the sequence. For example, if pulling wire is considered part of the electrical inwall activity and that activity is taking too long and doesn’t release the next activity, it may make more sense to move pulling wire downstream to level the work out.

Change the zones

Changing the zones may be a good solution if you realize the work is going faster or slower for some trades. The smaller the zones are, the faster you can go. This works great if the smaller zones still have a Takt time that is long enough to resolve problems in the time window. However, if that solution window is too small and there are too many constraints, then you may need larger zones (with longer corresponding Takt times) to accommodate the team’s ability to resolve problems. In general, I am all for creating a plan that starts with larger zones that you aim to break apart and go faster with time as the team gets more familiar with the plan.

Stop and catch up

If you are moving through the plan and realize that there are too many constraints and only 50% of the work can get completed as scheduled, then it makes more sense to stop and solve the problems. If you don’t stop now and there are many constraints out in the field, you will stop eventually, whether you want to or not.

Start slow

In the spirit of building confidence of the team with the plan, it’s a good idea to also start with a slower Takt time plan that the team can achieve with high reliability. This aligns with the philosophy of “lowering the river to reveal the rocks”. As the team gets more comfortable you can always adjust the takt time to accommodate their improved speed.

Move the work out of Takt

Sometimes we get a little ambitious with setting up the plan and place work in the Takt time sequence that doesn’t need to be there (e.g., does installing thermostats really need its own sequence?). This is an easy counter-measure to abuse, but it is always a question to ask when setting up the plan and executing the plan. Should we be planning this work to a Takt time or outside of it?

Visualize what was missed

In all circumstances, it is important to identify the work that was not completed. This is one of the benefits of executing to a Takt time plan and zones compared to no zones and working across full floors. The ability to see the plan unfold at a higher level of resolution allows you to see variation and improve. When the work is tracked visually it is easier communicate the problem to the entire team and rally behind a new plan to catch the work up.

Summary

There are many ways to get a takt train back on track. Regardless of what is done, it’s important to communicate how the plan is changing and get buy-in from team members so everyone keeps moving in the same direction and at the same speed. When a problem occurs, you want to deal with it right away and you don’t want to repeat the same mistakes again.


Featured Post

 

The Pocket Sensei - How to Teach Yourself to Train Your Mind

There's a revolution happening. It’s called learning while doing. Great projects are Lean — yet the majority of Lean initiatives fail. Lean is generally misunderstood to be about the tools we use rather than the people at the place where they work. Many Lean initiatives fail not because of the accessibility to Lean tools, but because leadership is unavailable when it is needed most. The leadership required to bring about and maintain such a tectonic shift seems scarce and difficult to develop.

Teaching Lean    Lean Culture Read more

 

10 Tips for Efficient and Effective Last Planner® System Sessions

This post follows on from my previous post about the “5 Levels of the Last Planner® System1 (LPS)” which provides a very brief overview of the LPS2. By using the following tips, a team is more likely to efficiently and effectively use the 5 levels of the LPS. Slipping back to old behaviours and routines regularly happens.

Last Planner Read more

 

What Can be Learned About Lean from an Arts Perspective

Have you ever thought about adding to your perspective on Lean and your Lean practices in design and construction? Most of what we understand about Lean is based on observations made by people with an engineering and scientific perspective on work. This way of looking at work has been extremely valuable, and still there is a sense that Lean may be missing something if it is to become more fully practiced. A recent workshop exploring the arts perspective of Lean was a first step in expanding our understanding of Lean and how to best help others see the value in the Lean approach to work.

Lean Culture     Read more

Copyright © 2015- Lean Construction Blog