How to Control Informal Work Packages with the Last Planner System

Loading the Elevenlabs Text to Speech AudioNative Player...

Recent research in Brazil identified that informal packages are executed frequently on construction sites, the exploratory studies estimate that about 30% to 35% of the tasks realized during the week were not planned and this percentage may have been higher if the Last Planner System was not implemented [1,2,3]. In this point, failure in the application of make ready process could be considered the main reason for the emergence of informal packages during the week.

An informal package is defined as a package that has not been planned at the weekly meeting but which ends up being executed during that week. Although these packages are usually neglected since it happens informally during the week and is not highlighted during the short-term and medium-term meeting, they can be detrimental to production, since their constraints are not usually removed systematically. It means that informal packages can increase Health & Safety concerns/risks, add additional activities that do not add value, change the sequence of construction tasks, increase the amount of unfinished works or reduce the quality. Others factors can explain the occurrence of informal packages, for example: (a) quality control is not integrated with production control; (b) construction is a type of site production where workers, materials and equipment move from one place to another in a large work area; (b) subcontractors normally put their interests ahead of the goals of the project because of traditional contracts that favor productivity rather than the termination of services, for example, contracts that pay per square meter executed.

The focus of this post is on highlight the root causes of informal work-packages and suggests how the Last Planner System can control it, since there are indicators that can be integrated into the routine of short-term and medium-term meeting to monitor the existence of these packages. This post presents an exploratory study carried out in a residential project in 2012. The point below presents two indicators that were developed to measure the incidence of informal packages. They can be integrated into the Last Planner System.

1. Percentage of informal work-packages
This is the number of informal work packages realized during the week divided by the total number of work-packages (formal and informal) executed. It t is expressed as a percentage. Behind all informal work packages, there is hidden information. For example, an informal work package could be a worker executing rework. To this point, the informal work packages would be classified as three categories:

  • Rework - tasks related to the correction of previously executed work;
  • Unfinished work - include tasks that were necessary due to the fact that a work-package had not been completed in the previous week;
  • New packages - consist of new work packages that had not been planned for that week.
2. Percentage of worker-hours spent in informal work packages
This indicator is based on a rough estimate of worker-hours spent on informal work packages divided by the total number of worker-hours spent during the week. Through this indicator, the management team can monitor the intensity of the work spent on the informal work package. As well as the previous indicator, the informal work packages could be analyzed as the three categories presented above: rework; unfinished work; and new packages.

The Exploratory Case Study
The study was carried out in a small building company that had a production planning & control system based on the Last Planner System, but not very effectively. The project of the study was a horizontal condominium, with 238 semi-detached houses, divided into 31 blocks, with 6,8,10,12, or 14 units, 47,05 m² or 56,8 m² per housing unit.

In the preliminary phase of the study, a diagnostic was taken to identify how the Last Planner System was implemented in the project. It was identified that the make ready process had implementation failures, since it did not happen systematically and when happened, just materials and workers constraints were analysed. The short-term planning had problems related implementation failures, since the weekly meeting did not encompass team leaders. Other problem identified during the diagnostic phase was the failure on integrating quality and production control. Since the check if the task was completed during the week did not consider the quality criteria, just if the goals of square meter was achieved. It was shown that when the quality control was realized, tasks that were considered completed weeks ago needed to be reworked during the week as an informal work package.

The purpose of the next phase of the study was to analyze the level of informal packages in the gypsum plastering process. Figure 1 shows that the number of informal packages in relation to the total number (formal+informal) of work packages is highly variable. In addition, it is possible to identify the incidences of informal packages such as rework, unfinished work and new packages during the week. This suggests a dispersion of the teams on site, since the non-removal of constraints generated disruptions in the gypsum plastering service of a house, causing the teams to disperse in search of another unit that can be worked. Furthermore, the effect of rework and unfinished work packages was very similar, since they required a worker to move back to a previous workplace, and make fairly small packages, sometimes taking more than one visit. It is happen due to this packages frequently were not considered in the make ready process.


Figure 1- Percentage of informal packages in gypsum plastering process

When evaluating the amount of working hours spent on different types of work packages, it was found that 71% of the worker-hours were spent on formal pre-planned work packages, while 19% were spent on rework activities and the final 10% were distributed between new work packages and unfinished works (Figure 2).

Figure 2- Distribution of worker according work packages

Conclusion
The quality of the antecedent service is one kind of constraints that the make ready process identify to remove before a task start. But, if there is failure to integrate the quality control with the production control or failure to implementing the Last Planner System in its entirety, informal work packages will arise during the week, as identified in exploratory study. In this point, the packages categorized into new were a result of the failure to implement make-ready process, since when a work team start the service without all constraints removed, they usually move to another work area with service front released. On the other hand, the packages categorized as unfinished work and rework were due to quality control, for example, when the task was considered complete without a quality check, the make ready process will not be effective, since the constraint “quality of the antecedent service” will not be removed. So, the make-ready process of the Last Planner System and rigorous quality control can help control the amount of informal work packages and rework. In conclusion, this study showed the importance of implementing the Last Planner System in its entirety and not to cherry-pick a few principles and practices of it, another important point is that monitoring the execution of informal packages during the week is possible to identify which principles or practices the management team should improve.

References

[1] Fireman, M. C. T., Formoso, C. T., and Isatto, E. L. (2013). “Integrating production and quality control: monitoring making-do and informal work packages.” 21th Annual Conference of the International Group for Lean Construction, (March 2016), 515–525.

[2] Ibarra, J.V., Formoso, C.T., Lima, C., Mourão, A., Saggin, A (2016). “Model for integrated production and quality control: implementation and testing using commercial software applications” In: Proc. 24th Ann. Conf. of the Int’l. Group for Lean Construction, Boston, MA, USA, pp. 73–82. Available at: www.iglc.net.

[3] Leão, C. F., Formoso, C. T., and Isatto, E. L. (2014). “Integrating Production and Quality Control with the Support of Information Technology.” 22h Annual Conference of the International Group for Lean Construction, 847–858.


Featured Post

 

An Introduction to Set Based Design

Set-based Design (SBD) is a design methodology that has many applications in the architecture, engineering, and construction (AEC) industry. It was discovered when researcher studied the engineering and design process at Toyota [1]. Known as the “second Toyota paradox”, the researchers were surprised to find that Toyota considered a broader range of possible decisions, produced more physical models, delayed key decisions longer, and yet they had the fastest and most efficient vehicle development cycle in the industry.

Lean Design     Read more

 

How Lean Leaders are Changing the Construction Industry

As an engineering professional a few years into my career, I’ve focused on building my skills in a way that allows me to contribute positively to my clients, my company, and the construction industry. I quickly realized that becoming a student of Lean would allow me to do just that. Through opportunities at my company, Southland Industries, and my involvement with the Lean Construction Institute’s Lean Leader group, I’ve learned how Lean practices can transform a project, and how important engaging the next generation of professionals is to full industry transformation.

Lean Culture Read more

 

 

11 Scrum Steps to Get Twice the Work Done in Half the Time

Before I began my Lean journey in 2009, I honestly never thought about my capacity. I paused and reflected on what I had learned about applying Lean. My entry point was “Lean Thinking” by Womack and Jones, but even practicing the principles and some tools wasn’t increasing my management capacity beyond my first-year gains. I was a chronic workaholic and after beginning to practice Lean I was down to a consistent 55-60-hour workweek with only occasional Saturdays. Something was missing, I wasn’t improving. I had reached a plateau. I wasn’t satisfied.

Scrum Read more

Copyright © 2015- Lean Construction Blog