A Simple Framework for Putting Integrated Project Delivery (IPD) Into Action

Recent research in Brazil identified that informal packages are executed frequently on construction sites, the exploratory studies estimate that about 30% to 35% of the tasks realized during the week were not planned and this percentage may have been higher if the Last Planner System was not implemented [1,2,3]. In this point, failure in the application of make ready process could be considered the main reason for the emergence of informal packages during the week.

An informal package is defined as a package that has not been planned at the weekly meeting but which ends up being executed during that week.

Last Planner Read more